Greetings from One City Center in Downtown Durham! February was a big month for construction -- our floor-to-ceiling glass has almost been completely installed, the crane has been removed, and we continue to build out our apartment, condo, and amenity spaces.

Here are a couple major updates ::

  • Kitchen counter tops are being installed on the 7th floor
  • Sheetrock painting has started on the 7th floor
  • Turf has been installed on 6th floor amenity deck
  • Rooftop hot tub molding has been poured
  • Rooftop window installation for the clubhouse has started

Stay tuned for more updates coming soon! 